Phase Two completes the master plan for Marie Selby Botanical Gardens, the 15-acre bayfront campus at Mound Street and South Palm Avenue in downtown Sarasota, where Sarasota Bay meets Hudson Bayou, at 1534 Mound Street, under way since December 2025 and set to finish in November 2028. Financed with $41.9M from Capital Trust Agency in July 2026.
Sweet Sparkman Architects designed the phase, with OLIN as landscape architect, Willis A. Smith Construction as construction manager and Kimley-Horn on civil engineering. The centerpiece is a new conservatory built to put far more of Selby's living collection on public view, joined by display and exhibition houses and a learning pavilion, all wrapped into the replanted gardens Phase One began. Phase One delivered the welcome plaza, the Steere Family Plant Research Center and a rooftop solar array over structured parking, giving the campus its new front door on Mound Street. Selby is a research institution as much as a public garden, and the second phase is built around showing the science rather than storing it.
Vertical construction began on Phase Two after the gardens closed a 41.9 million dollar bond sale, with Willis Smith Construction as construction manager and OLIN on the landscape.
selby.orgSelby Gardens executed a $41.9M tax-exempt bond sale; $59.7M of $60.9M raised. Phase Two = 32,605 sf conservatory + 2,760 sf learning pavilion.
selby.orgSelby Gardens commits to Phase Two of its downtown master plan, conservatory complex and learning pavilion, at 66% of its $60.9M campaign goal.
yourobserver.comThe outlook for Marie Selby Botanical Gardens Phase Two
Timing and similar projects, read from every development in our database.
Nearby and comparables
Within 2 miles of it, nearest first.
0.2 mi awayThe Palm 625 SarasotaResidencesDowntown SarasotaOpening SoonView project
0.5 mi awayMira Mar ResidencesResidencesDowntown SarasotaUnder ConstructionView project
0.6 mi awayWaldorf Astoria Residences SarasotaMixed-UseDowntown SarasotaExpected 2029View project
0.7 mi awayThe High LineResidencesDowntown SarasotaAnnouncedView project
0.7 mi awayThe Owen Golden Gate PointResidencesGolden Gate PointNow openView project
0.8 mi awayBayside NorthResidencesRosemary DistrictUnder ConstructionView project
0.8 mi awayThe Edge SarasotaResidencesRosemary DistrictOpening SoonView project
0.9 mi awayOne Park SarasotaResidencesThe QuayUnder ConstructionView project
1.0 mi awaySaravelaResidencesNorth TrailExpected 2029View project
1.0 mi awayThe Ritz-Carlton Residences Sarasota BayResidencesThe QuayExpected Dec 2026View projectThe projects most like it in its market. Tap one to go head to head.
Companies and contacts
Every firm on Marie Selby Botanical Gardens Phase Two, the office nearest it, and the people who work on it.
Frequently asked
Where is Marie Selby Botanical Gardens Phase Two located?
Marie Selby Botanical Gardens Phase Two is located in Sarasota.
When will Marie Selby Botanical Gardens Phase Two be completed?
Marie Selby Botanical Gardens Phase Two is under construction, with completion expected in November 2028.
Who is developing Marie Selby Botanical Gardens Phase Two?
Marie Selby Botanical Gardens is the developer behind Marie Selby Botanical Gardens Phase Two.
Who designed Marie Selby Botanical Gardens Phase Two?
Marie Selby Botanical Gardens Phase Two was designed by Sweet Sparkman Architects.
Who is building Marie Selby Botanical Gardens Phase Two?
Marie Selby Botanical Gardens Phase Two is being built by Willis Smith Construction.
1.2 mi away
5.2 mi away