Under Construction

Belle Meade Village

Nashville · Mixed-Use

Belle Meade Village is a 15.5-acre mixed-use redevelopment at the gateway to Belle Meade in Nashville, Tennessee, transforming the former Belle Meade Plaza into a walkable retail-and-residential district by AJ Capital Partners.

Official Website
Last verified Jul 17, 2026
2.4 yrs to delivery
43%
AnnouncedBreaking GroundConstructionOpening SoonNow Open
Delivers in phases · 1 component
10.25
Start
2028
Full build-out
78
Keys
92
Units
8
Floors
Scroll for details
The story so far
Announced · Belle Meade Village Feb 29, 2024
oftmw.com
Announced · 1 Iris Lane, The Residences at Belle Meade Village Feb 29, 2024
oftmw.com
Broke ground · Belle Meade Village Oct 2025Construction/site mobilization commenced October 2025 (excavation/blasting began November 2025) per CityNowNext
citynownext.com
Broke ground · 1 Iris Lane, The Residences at Belle Meade Village Oct 2025Construction/site mobilization commenced October 2025 (shared district groundwork) per CityNowNext
citynownext.com
Sales launched · Belle Meade Village Nov 2025Condo sales launched Nov 2025; ~40% pre-sold within three months
commercialobserver.com
Sales launched · 1 Iris Lane, The Residences at Belle Meade Village Nov 3, 2025Sales gallery opened Nov 3, 2025 (by appointment); condos already reported ~40% pre-sold starting at $2.5-3M per Commercial Observer/Axios Nashville
citynownext.com
Financing secured · Belle Meade Village Jan 23, 2026$475M construction loan from Barings closed Jan 23, 2026, financing the 15.5-acre mixed-use district (92 condos, 40+ retail storefronts, boutique hotel up to 78 keys)
commercialobserver.com
Financing secured · 1 Iris Lane, The Residences at Belle Meade Village Jan 24, 2026$475M Barings construction loan (whole Belle Meade Village) closed 2026-01-24; residences slated 2028; GFA est. from 92 units x ~3,200 sf avg + 16,000 sf amenities
commercialobserver.com
Going vertical · Belle Meade Village Apr 2026Vertical concrete construction underway following completion of controlled blasting/excavation (50 ft below grade for 900-space underground garage) on April 3, 2026, per CityNowNext
citynownext.com
Going vertical · 1 Iris Lane, The Residences at Belle Meade Village Apr 2026Vertical concrete underway April 2026 (foundations Dec 2025, final blasting Apr 3); construction started Oct 2025. Backfill address+country.
citynownext.com
Expected opening · Belle Meade Village 2028
Expected opening · 1 Iris Lane, The Residences at Belle Meade Village 2028 est.
Milestones are dated to when they actually happened and linked to their source. This record fills in over time as TMW tracks the project.
About the project

Belle Meade Village is a 15.5-acre mixed-use redevelopment at the gateway to Belle Meade in Nashville, Tennessee, transforming the former Belle Meade Plaza into a walkable retail-and-residential district by AJ Capital Partners. The plan pairs a seven-building retail town square of more than 40 storefronts, chef-driven restaurants, a private members' club and a boutique hotel — arranged around a landscaped courtyard anchored by an antique carousel — with 1 Iris Lane, two intimate 46-residence condominium buildings set within a five-acre private park and greenway. Architecture is led by Hartshorne Plunkard Architecture and Hastings Architecture, delivering a cosmopolitan village of shopping, dining, wellness and luxury living at one of Nashville's most affluent crossroads.

Developer & design
The Nashville market 93 · Saturated supplyBelle Meade 23-project pipeline · 4,080 residences and keys · peak Late ’27 Explore the market →
Common questions

Frequently asked

Where is Belle Meade Village located?

Belle Meade Village is located in Nashville.

When will Belle Meade Village be completed?

Belle Meade Village is under construction, with completion expected in 2028.

How will Belle Meade Village be built out?

Belle Meade Village is a phased, multi-component development with 1 tracked component delivering on a rolling schedule. Full build-out is expected in 2028.

Who is developing Belle Meade Village?

AJ Capital Partners is the developer behind Belle Meade Village.

Who designed Belle Meade Village?

Belle Meade Village was designed by Hastings Architecture.