Under Construction

East Bank

Scroll for details
The story so far

East Bank is Nashville's transformational riverfront district on the east bank of the Cumberland River, directly across from downtown, spanning roughly 550 acres guided by Metro Nashville's East Bank vision plan and the East Bank Development Authority, under way since February 2024, with full build-out in 2031. Financed with $120M in May 2026.

Riverfront. A 550-acre site. At its core is Eastpoint, a 30-acre Metro-owned mixed-use neighborhood master-developed by The Fallon Company, planned around walkable tree-lined streets, bike lanes and a 1.5-acre central plaza framed by about 50,000 square feet of multi-level shops and restaurants, a 600-room hotel, offices and residential towers, with a master development agreement committing 1,550 homes and 99-year affordability protections. Its first building, Eastpoint Flats, developed with Elmington Capital, is a fully affordable block of 323 apartments with a childcare center and neighborhood retail. The wider district also takes in the new enclosed Nissan Stadium for the Tennessee Titans, the relocated Tennessee Performing Arts Center designed by Bjarke Ingels Group, Oracle's riverfront campus and a reconnected public riverfront park system.

Expected opening · Oracle Campus 2031
Expected opening · Parcel C1 Hotel Dec 2030
Expected opening · Eastpoint 2030
Expected opening · Tennessee Performing Arts Center 2030 est.
Expected opening · East Bank 2030
Expected opening · Oracle Pedestrian Bridge 2028 est.
Expected opening · Nobu Hotel Nashville 2028
Expected groundbreaking · Parcel C1 Hotel Oct 2027
Expected opening · Tennessee Titans Stadium Feb 17, 2027 est.
Expected groundbreaking · Tennessee Performing Arts Center 2027 est.
Under construction · East Bank Mid 2026

Eastpoint Flats (Parcel G) broke ground May 28 2026 with vertical construction commencing within ~60 days.

nashville.gov
East Bank hotel slips past Super Bowl · East Bank Sep 23, 2026

Fallon told the East Bank Development Authority the 600-room Eastpoint hotel will break ground in Q3 2027 and open in Q3 2030, missing Super Bowl LXIV and the spring 2029 target (Fox 17, WKRN).

fox17.com
Flagship hotel slips · Eastpoint Sep 22, 2026

Eastpoint's 600-room Parcel C hotel now targets a Q3 2027 start and Q3 2030 opening.

wsmv.com
Flagship hotel delayed · Eastpoint Sep 22, 2026

The Fallon Company says the 600-room Eastpoint flagship hotel beside the new stadium will miss Super Bowl 2030 as design wraps up; construction is now slated to start July 2027, with the sports authority board weighing options Oct 27 (WSMV).

wsmv.com
Parcel C hotel slips past Super Bowl · Eastpoint Sep 2026

Fallon now targets a Q3 2027 start and Q3 2030 opening for the anchor hotel, residential and retail parcel, later than Metro's spring 2029 timeline.

axios.com
Oracle bridge moves into permitting · Oracle Pedestrian Bridge Sep 2026

A Tennessee Department of Environment and Conservation filing sets the 863-foot, 16-foot-wide Foster + Partners span on a two-year build, landing at Taylor Street in Germantown's Neuhoff District on the west and River North Boulevard at Cowan Street on the east. Construction has not started.

fox17.com
Oracle files final site plans · Nobu Hotel Nashville Sep 2026

Oracle's final site plan for its River North campus on Nashville's East Bank places the luxury hotel complex at the campus's southern end beside the Landings at River North, in a public-facing zone that could also hold a park and retail; construction timing not yet set (The Tennessean).

yahoo.com
Oracle files final site plans for its $4.5B Nashville HQ · Oracle Campus Sep 2026

The 82-acre River North campus is detailed at 23 buildings around a central lake with 2M+ sq ft of office, a Nobu hotel and riverfront park, with demolition and site prep underway and groundbreaking still unscheduled.

therealdeal.com
Seats going in, roof nearly done · Tennessee Titans Stadium Sep 2026

About 10,000 of 60,000 seats are installed, the ETFE roof is due to finish by mid-October and roughly 2,300 workers are on site daily, with early turnover areas set for Jan. 7, 2027 (WKRN).

wkrn.com
Coming soon · Tennessee Titans Stadium Sep 2026 est.

Roof cable net complete, seats going in; building targets February 2027 completion (within ~5 months), corroborated by Fox17. Re-applied after a clobbered commit.

wsmv.com
Under construction · Eastpoint Sep 2026 est.
Roof cable net complete · Tennessee Titans Stadium Aug 2026

The ETFE cable net system is finished, two of four cranes are down, seat installation is about to begin and full enclosure is expected within months, with the stadium on track to open February 2027 (WSMV).

wsmv.com
Broke ground · East Bank Jun 2026 est.

Fallon Company broke ground May 28 2026 on Eastpoint Flats, first building of its 30-acre East Bank/Eastpoint district.

nashville.gov
Financing secured · Eastpoint Jun 2026

Elmington Capital closed $80M in construction loans for Eastpoint Flats, the 323-unit all-affordable first building of Eastpoint (Parcel G, 501 S. Second St.).

apartmentbuildings.com
First shovels on the riverfront · East Bank May 28, 2026

The Fallon Company and Elmington Capital broke ground on Eastpoint Flats, the opening building of the thirty-acre initial development area, an all-affordable block of 323 apartments with an 8,420-square-foot childcare center and 12,600 square feet of retail. The master development agreement behind it commits 1,550 residences over the next decade and locks affordability in for 99 years.

oftmw.com
Broke ground · Eastpoint May 28, 2026

Fallon Company and Elmington Capital broke ground on Eastpoint Flats, the first building (323 affordable units) in the 30-acre East Bank district.

oftmw.com
Nashville lands Super Bowl LXIV · Tennessee Titans Stadium May 19, 2026

NFL owners voted to award the February 2030 Super Bowl to the new Nissan Stadium, the first ever held in Tennessee.

nfl.com
Renderings and construction timeline released · Oracle Pedestrian Bridge May 14, 2026

Oracle's TDEC permit application sets an August 2026 construction start and a two-year build for the 863-foot, 16-foot-wide steel-mast and cable-supported span, landing at Taylor Street in Germantown's Neuhoff District on the west and River North Boulevard at Cowan Street on the east.

nashvillepost.com
Announced · Parcel C1 Hotel May 9, 2026
oftmw.com
Announced · Eastpoint May 9, 2026
oftmw.com
Crews begin raising the roof · Tennessee Titans Stadium May 2026

Strand jacks started lifting the ETFE roof cable net into place, with full enclosure targeted for October 2026 and the roof finished in early 2027.

nashvillepost.com
Eastpoint phase one renderings released · East Bank May 2026

Master developer The Fallon Company unveiled concept images for Parcel C, pairing a 600-room hotel near the stadium with residences (10% affordable) and roughly 50,000 square feet of multi-level retail and dining around a 1.5-acre central plaza and the Nashville Post.

oftmw.com
Financing secured · East Bank May 2026

THDA committed $120M+ ($52M tax-exempt bonds + tax credits) to Eastpoint Flats, announced at the groundbreaking.

oftmw.com
Rezoning approved · The East Bend Apr 21, 2026

Metro Nashville Council voted unanimously to grant final approval to the rezoning of the 47-acre former PSC Metals scrapyard after working through 28 amendments, clearing TEB LLC to build The East Bend with towers of up to 40 stories, and Mayor Freddie O'Connell signed the legislation.

wsmv.com
Design unveiled · Tennessee Performing Arts Center Apr 16, 2026

BIG and William Rawn Associates revealed a 307,000-square-foot, $600M East Bank campus holding a Grand Broadway theater, a dance and opera hall, a black box and a cabaret space behind a facade of bundled aluminum tubes.

oftmw.com
Stadium passes 75% complete · Tennessee Titans Stadium Mar 2026

The build was three-quarters finished at the end of March 2026 with roughly 2,000 workers on site daily.

nashvillescene.com
Metro Council approves East Bank ground lease · Tennessee Performing Arts Center Jan 2026

Council passed on final reading the 35-year ground lease letting TPAC build its new campus on Metro land, with TPAC covering roughly $18.6M of infrastructure (also WKRN).

nashvillescene.com
Broke ground · Oracle Campus Jan 2026

Land-clearing only: demolition and grading permits pulled, zoning change still pending; vertical construction not yet begun.

therealdeal.com
Announced · Oracle Pedestrian Bridge 2026 est.
Announced · Oracle Campus 2026 est.
Construction team named · Tennessee Performing Arts Center Dec 8, 2025

R.C. Mathews Contractor, JE Dunn Construction and Don Hardin Group will build TPAC's new East Bank venue as a joint venture on the 4.4-acre site.

rcmathews.com
Topped out · Tennessee Titans Stadium Nov 21, 2025

Final steel beam placed on the $2.1B stadium, topping out the structure.

constructiondive.com
Financing secured · Tennessee Performing Arts Center Nov 20, 2025

Metro Nashville–TPAC East Bank relocation & infrastructure cost-share agreement reached (anchors ~$600M project, $500M state + private match).

axios.com
Tenant announced · East Bank Nov 19, 2025

Agreement reached for the Tennessee Performing Arts Center to relocate to the East Bank as the district's anchor cultural institution; TPAC targets an early-2027 groundbreaking and 2030 completion. Per Nashville Banner, corroborated by WKRN.

nashvillebanner.com
Rezoning approved · Nobu Hotel Nashville Oct 2025

Metro Council approved the key rezoning for Oracle's River North campus, including the Nobu hotel, clearing one of the final hurdles (FOX 17; NewsChannel 5).

fox17.com
Announced · The East Bend Aug 2025

47-acre former PSC Metals riverfront scrapyard on Nashville's East Bank sold for $245M to a David Byerley–led group (TEB LLC) for redevelopment as The East Bend, a multi-decade mixed-use neighborhood.

aol.com
Halfway there · Tennessee Titans Stadium 2025

Construction reached halfway point mid-2025 (ESPN).

espn.com
Announced · Nobu Hotel Nashville 2025 est.

Nobu Hospitality announces a 120-room Nobu Hotel and Restaurant Nashville designed by Foster + Partners within Oracle's River North campus on the East Bank.

lodgingmagazine.com
Announced · Tennessee Performing Arts Center 2025 est.
Announced · East Bank Mar 1, 2024
oftmw.com
Broke ground · Tennessee Titans Stadium Feb 29, 2024

New Nissan Stadium groundbreaking Feb 29, 2024.

nfl.com
Announced · Tennessee Titans Stadium 2024 est.
Milestones are dated to when they actually happened and linked to their source. This record fills in over time as TMW tracks the project.
TMW IntelligenceVerified Oct 30, 2026
AnnouncedBreaking GroundConstructionOpening SoonNow Open
Delivers in phases · 8 components

The outlook for East Bank

Timing and similar projects, read from every development in our database.

The Nashville market 40-project pipelineEast Bank 17,613 residences and keys across the projects in our database Explore the market →
Pro tools
Compare projectsSide by side with its nearest compsAnalyze the marketModeled pricing, comps and timing

Companies and contacts

Every firm on East Bank, the office nearest it, and the people who work on it.

Project website
Architect
Marketing
Common questions

Frequently asked

Where is East Bank located?

East Bank is located in Nashville.

When will East Bank be completed?

East Bank is under construction, with completion expected in 2031.

How will East Bank be built out?

East Bank is a phased, multi-component development with 8 tracked components delivering on a rolling schedule. Full build-out is expected in 2031.

Who is developing East Bank?

Metro Government of Nashville is the developer behind East Bank.

Who designed East Bank?

East Bank was designed by Perkins Eastman.